How long it takes to permit a NYC restaurant.
Restaurant Liquor (RL) is faster than OP — narrower CB review, no 500-foot rule. DOH Article 81 + FDNY hood install is the typical critical path. If wood/charcoal grill, FDNY F-58 becomes critical.
NYSLA On-Premise
Restaurant Liquor (RL) — narrower scope than OP; 500-foot rule does not apply to bona-fide restaurants
DOB PW1
Architect-sealed plans filed via DOB NOW. ALT-2 (no use/egress change) typical for 2nd-gen restaurant. ALT-1 needed for change-of-use or POA threshold trigger.
⚠ Plan-examiner objections add 2-6 weeks per round. Expediter relationships materially shorten cycle time.
DOH Article 81
Required for new food service permit. Plan review covers refrigeration, handwash sinks, food protection, dishwashing, restrooms.
⚠ 3-compartment sink + handwash sink placement is the most common objection. Pre-design with kitchen designer to avoid 2-4 week re-submittal cycles.
FDNY Hood/Ansul
NFPA 96 Type I commercial hood with UL 300 wet-chemical suppression. Plan review + post-install inspection.
⚠ Hood approval gates DOH operating permit. Wet-chemical suppression must be serviced every 6 months by FDNY-certified contractor.
FDNY F-59
Required when fire alarm system is installed. Cert holder must be on payroll. Often bundled with FDNY S-13 (sprinkler) certification.
DOB C of O / TCO
Final sign-off after all inspections (DOB + FDNY + DOH coordinated). TCO at 90% construction is the standard path to opening, full C of O follows within 60-180 days.
⚠ TCO is gated on every other agency clearing its inspection. Single-trade hold-ups can delay opening by 4-8 weeks.
DOH FSE Permit
Issued after pre-operational inspection passes. Permit valid 1-2 years, renewable. Includes Letter Grade inspection cycle.
⚠ Pre-op inspection scheduled only after all construction punch-list items closed. Schedule 2-3 weeks ahead.
DOH FPC
At least one FPC-certified manager on duty during all operating hours. 15-hour online course + exam.
The full restaurant opening playbook →
See every vendor category, milestone, and capital line you need — not just the permits.